Project understanding
Three facilities. 630 MWac. One construction programme.
Approximately 36 km north of Northam, Limpopo, on around 1,525 ha. REIPPPP Bid Window 7, per the Infinity Power synopsis of 3 March 2025.
Locality
Spitskop PV cluster locality map

Facilities
Explore each site
Vanadium PV
150MWac
182.99 MWp DC
- Tracker
- Single-axis, N–S, 1P
- Row pitch
- 7.0 m
- Collection
- 33 kV
- Transformers
- 2 × 100 MVA, 33/132 kV
- Grid connection
- ≈22 km, 132 kV Twin Tern line
- Switching
- Switching station and Spitskop MTS feeder bay interface
Construction considerations
- Tighter 7.0 m row pitch affects plant movement between rows
- Longer-lead feeder bay interface at Spitskop MTS
Comparison
Side by side
| Vanadium PV | Palladium PV | Copper PV | |
|---|---|---|---|
| AC capacity | 150 MW | 240 MW | 240 MW |
| DC capacity | 182.99 MWp | 292.79 MWp | 292.79 MWp |
| Row pitch | 7.0 m | 7.5 m | 7.5 m |
| Transformers | 2 × 100 MVA, 33/132 kV | 2 × 150 MVA, 33/132 kV | 2 × 150 MVA, 33/132 kV |
| Grid line | ≈22 km, 132 kV Twin Tern line | ≈30 km, 132 kV single-circuit Twin Tern line | ≈26 km, 132 kV double-circuit Twin Tern line |
Modules
TOPCon, ≥625 Wp
Trackers
Single-axis, N–S, 1P
Collection
33 kV
Evacuation
132 kV
Design life
30 years
Corrosion
C3
Wind
36 m/s 3-s gust
Ambient
42°C max. avg.
Local content
36.17%
Technical interfaces
From module to Spitskop MTS
01
PV arrays (DC)
02
Inverters & 33 kV collection
03
Plant substation 33/132 kV
04
132 kV line & switching station
05
Spitskop MTS
Sector context
National transmission context
The Transmission Development Plan 2025 (Rev 2) sets out grid development that includes the REIPPPP programme, most recently Bid Window 7. This is national sector context only and is separate from the specific Spitskop project contract.
01
Transmission Development Plan 2025 Rev 2
02
REIPPPP Bid Window 7 preferred bidders
03
Preferred bidders appoint EPC
04
EPC appoints construction contractors on their execution methodology
