Engagement
Clarifications and next steps
Open technical queries are logged transparently rather than resolved silently.
Technical clarification register
TQ-001Capacity figuresMain capacity table and later single-line diagrams in the developer synopsis (3 March 2025) show differing values. Confirmation of governing figures requested from the EPC.Open
TQ-002DC vs AC basisThe '770 MW' figure is understood as ≈770 MWp DC (768.57 MWp), not MWac. Confirmation requested.Open
TQ-003Package boundariesDinga's construction package boundaries remain subject to EPC allocation.Open
Proposed next steps
From proposal to package allocation
01
Clarification meeting with EPC project leadership
02
Confirmation of preferred work packages
03
Contractor due diligence & site visit
04
Pricing and subcontract terms