Dinga Engineering

Engagement

Clarifications and next steps

Open technical queries are logged transparently rather than resolved silently.

Technical clarification register

TQ-001Capacity figuresMain capacity table and later single-line diagrams in the developer synopsis (3 March 2025) show differing values. Confirmation of governing figures requested from the EPC.Open
TQ-002DC vs AC basisThe '770 MW' figure is understood as ≈770 MWp DC (768.57 MWp), not MWac. Confirmation requested.Open
TQ-003Package boundariesDinga's construction package boundaries remain subject to EPC allocation.Open

Proposed next steps

From proposal to package allocation

  1. 01

    Clarification meeting with EPC project leadership

  2. 02

    Confirmation of preferred work packages

  3. 03

    Contractor due diligence & site visit

  4. 04

    Pricing and subcontract terms